General Features & Process Description


Heavy Water Plant at Hazira (also known as Hazira Ammonia Extension Plant - HAEP), employs the ammonia-hydrogen exchange mono-thermal process. The plant is located at a distance of about 16 km from Surat city. Work on HWP (Hazira) commenced in August 1986 and the plant was commissioned in January 1991.

Process Description

This plant comprises of two streams consisting of two separate isotopic exchange units, final enrichment units, final production units & cracker units, but a common ammonia synthesis unit. Feed synthesis gas (a mixture of one part of nitrogen and three parts of hydrogen containing deuterium from the Ammonia plant) is routed through the plant at a flow rate of about 96 T/Hr. at a pressure of about 181-220 kg/cm². The pressure of the gas is first raised by 40 kg/cm² by a booster, to take care of pressure drop in the plant. It is then cooled in a heat exchanger by the outgoing cold gas returned from the plant. The gas is thereafter passed through a purification unit. In this unit the oxygenated impurities contained in the gas are removed and the gas is saturated with ammonia. The purified synthesis gas saturated with ammonia is then passed through the first isotopic exchange tower working at minus 25 °C where deuterium in the gas is transferred to a counter current stream of liquid ammonia containing potassium amide catalyst fed from the top of the tower. The deuterium enriched ammonia from the bottom of the exchange tower is then fed to the second isotopic exchange tower where it gets further enriched by coming in contact with the enriched synthesis gases obtained by cracking of enriched ammonia.  A part of the enriched gas and liquid from the second isotopic exchange tower is then taken to the final enrichment section where the concentration of deuterium in the ammonia can be further increased as desired upto 99.8%.  Finally, the enriched ammonia so obtained is made free of the catalyst and is cracked. A portion of this enriched synthesis gas is burnt with dry air to produce heavy water.  However, for reasons of better recovery efficiency the concentration of deuterium in ammonia in the final enrichment section is kept low so as to produce heavy water of about 60% which is then vacuum distilled to produce heavy water of nuclear grade.

The cold synthesis gas depleted in deuterium from the first exchange tower, before its return to Ammonia Plant, is heated by the incoming feed gas and is passed through an ammonia synthesis unit. In this unit, a portion of the synthesis gas equivalent to the amount of the ammonia cracked in the crackers is converted into liquid ammonia and fed to the top of first exchange tower.  The rest of the depleted synthesis gas equivalent to the feed gas supplied is returned to the ammonia plant. The power to the plant is supplied by Gujarat State Electricity Board from their 66 KV grid.  The fuel used for heating of the crackers of the plant is natural gas which is supplied by GAIL.

Some of the special features of the plant are:

  1. HWP (Hazira) is the second heavy water plant in the country based on the ammonia-hydrogen exchange process which has been set up without foreign collaboration.  The basic design of isotopic exchange unit was developed in-house.

  2. The plant adopts the latest technology using micro-processor based distributed digital control system for instrumentation and process control instead of the conventional pneumatic analogue system.   The system provides supervisory and monitoring functions for field control stations.   It displays and records data acquired from the plant system and has facilities for data logging and printing alarm messages.

  3. This plant comprises of two streams with some common units like synthesis unit, sub-station, inert gas unit, instrument air unit, catalyst preparation unit, cooling towers etc.

  4. Completion of the project has been successfully achieved without any time overrun.
 
Salient Data of Heavy Water Plant (HAZIRA)
1. Process Ammonia-Hydrogen Mono-thermal Exchange
2. Process Know-how Departmental
3. Capacity of the Plant 80 MT / Year
4. Date of Commercial Production 15.01.1991
5. Capital Cost of the Plant 264.39 Crores
6. Area of the Plant 35 Hectares
7. Operating Pressure 220 Kg / Cm²
8. Feed Synthesis Gas Flow Rate 96 T/Hr (48 T/Hr per stream)
9. Total Weight of Structure 7500 MT approx.
10. Total Weight of Equipments 4400 MT approx.
11. Weight of Heaviest Equipment 425 MT
12. Maximum Diameter of Equipment 2.35 Meters
13. Maximum Height of Towers 40 Meters
14. Total Length of Piping 217 Kms. approx.
15. Total Length of Electrical Cables 300 Kms. approx.
16. Power Consumption 310000 Units / Day

17.

Natural Gas Consumption 76000 SM3 / Day

18.

Make up Water Consumption 2800 M3 / Day

19.

DM Water Consumption 125 M3 / Day
 
 
Right To Information (RTI) act -2005
Immovable Property Return
Plants at a Glance
New Activities
Value Added Services
Corporate Membership
Tenders (above Rs. 10 Lakh)
Tenders (Upto Rs. 10 Lakhs)
e-Tendering Portal
RPUM-Purchase Orders
Recruitment
Recruitment Result
FAQs
Archive
About HWB & Plants
Holiday List
Site Map
Copyright Policy
Privacy Policy
Terms of Use
Linking Policy
Disclaimer
Contact Us
Postal Address of HWB & HWPs
Liaison Officers of HWB & HWPs
Web Information Manager (Content Manager)
Awards and Achievements
Screen Reader

   Link to Other DAE Units
india.gov.in
    Last Updated: 31 March,2015
This website belongs to Heavy Water Board, a Unit of Department of Atomic Energy, Government of India and all the matter published on it is owned by and a copyright of the organization.

WebSite developed and hosted by Heavy Water Board, Mumbai.