HWPM/M-P/102/MTA-2020/19
Complete overhauling including seal inspection work of H2S gas boosters in XU-II during MTA-2020 in Main Plant of HWP(M).
Complete overhauling including seal inspection work of H2S gas boosters in XU-II during MTA-2020 in Main Plant of HWP(M).
Servicing and testing of Butterfly valves & check valves of Main cooling water pumps during MTA-2020 in Main plant of HWPM.
Removal and re-erection of Control valves during MTA-2020 in Main plant of HWPM.
Chemical Cleaning of the Cooling Water Heat exchangers aof Exchange Units.
1) XU-II purge tower internal cleaning and packing replacement.
2) XU-II towers/tanks sump cleaning.
3) XU-II product stripper internal cleaning and packing replacement.
Last Updated: 17-06-2026