2013

Commissioning and Operation of 2KA sodium test cell at HWP, Baroda

2013

Commissioning of 18O Water Pilot plant at HWP, Tuticorin

05-Feb-2013

Achieved 86% 18O concentration in prototype 18O distillation column at HWP, Tuticorin

2012

Trial operation of Boron Carbide Pelletisation Plant at HWP, Manuguru

01-Aug-2012

Completed supply of 10B enriched Boron for first core of PFBR.

13-Apr-2012

Highly enriched 11B (>99.7% IP) delivered to US for in-situ evaluation.

2012

Commissioning of Solvent Synthesis Pilot Plant (VSSP) at HWP, Tuticorin

31-Mar-2012

First Supply of D-labeled compound to BRIT for sale.

04-Feb-2012

Inauguration of Versatile Solvent Synthesis Pilot Plant (VSPP) facility by Dr. S Banerjee, then Chairman AEC at HWP, Talcher

21-Oct-2011

Commissioning for conversion of Enriched BF3 Complex into KBF4 at HWP, Talcher