Date | Subject |
---|---|
31-Mar-2019 |
HWP, Hazira has achieved record lowest specific energy consumption of 22.92 GJ/kg D2O, for any Heavy Water Plant during financial year 2018-19. |
31-Dec-2018 |
Environment Clearance Received for Solvent Extraction Plant being set-up at HWP, Tuticorin |
Nov-2018 |
Commissioning of Boric Acid Drying Unit at HWP, Talcher |
15-May-2018 |
Inauguration of Enriched BF3 Gas Generation Facility by Hon’ble President of India Shri Ram Nath Kovind at HWP, Talcher |
30-Mar-2018 |
Erection and Commissioning of 3 MW Steam Turbine Generator at HWP, Kota |
21-Oct-2017 |
Laying of Foundation stone for Solvent Extraction Plant at HWP, Tuticorin |
17-Apr-2017 |
Laying of Foundation stone for Solvent Production Plant at HWP, Tuticorin |
Nov-2016 |
Commissioning of 24 Unit NH3 - Water Exchange System at HWP, Hazira |
Jun-2016 |
Commissioning of Crystallizer Unit at HWP, Kota |
28-Sep-2015 |
Erection/Commissioning of Boric Acid Purification Unit at HWP, Talcher |