2008

Installation of one additional distillation unit (DU) column taken up to cope up with the enhanced feed processing in XUs at HWP, Manuguru

2007

H2S gas recovery from sour oil system commissioned at HWP, Manuguru

25-Feb-2007

First export of Heavy Water for non-nuclear application (to M/s Spectra Gases Inc. USA.)

14-Sep-2006

Steam line from RAPS 3 &4 commissioned at HWP, Kota

2006

Power Export started for the first time from CPP, HWP, Manuguru

16-Sep-2006

First supply D2 gas for non-nuclear application (to M/s Sterlite)

14-Jul-2006

Pilot scale production of 3rdSolvent TOPO[TOPS-08] at HWP, Talcher

15-Jan-2006

First Sodium metal collection at Sodium Metal Plant, HWP, Manuguru

2005

First consignment of TBP from Talcher to NRG, Tarapur.

06-Nov-2004

Then Chairman (AEC), Dr. Anil Kakodkar inaugrated the Vapour Abosrption Refrigeration System and laid Foundation Stone for Sodium Metal Production Facility & poured concrete for equipment foundation for Boron Enrichment facility at HWP (Manuguru).